The Background
The Paseo Community Development District (CDD), is a large and vibrant master association community based in Fort Myers, Florida. When we began our conversations, their irrigation was managed by two separate pump stations serving the community's north and south sections.
The south station, which handled the largest part of the community, was fundamentally flawed in its original design. It was configured from the start as two separate 50 horsepower enclosures and a jockey, resulting in distinct systems that did not communicate.
Building on our initial assessment, we then identified an opportunity to modernize this setup into a single, integrated, and more efficient system. Key to this modernization effort was the installation of an almost 700-feet long new 8-inch pipeline designed to make the most of the increased capacity of the new pump station.









